When we acknowledge your application, you will receive an approval notification. This notification will detail the schedule of building regulation inspection notifications - which will outline the stages where we need to make a site inspection.
We will inspect your site at certain points, to make sure that your project is meeting building regulations. Additional inspections may also be required during the work.
Under building control regulations - for any type of application and work - you need to notify us at the following stages (which may or may not need a physical inspection). The minimum notifications we require are:
Start of work – notice required two days prior to starting work on site
Completion of work - notice of completion of works is required five days prior to the date on which work is considered complete. A completion notice by a person carrying out building work must be completed by all dutyholders and returned to us not more than five days after the work has been completed. Failure to complete and return this may result in a delay in the issue of the certificate of completion
Types of inspections which need 24 hours notice
Uncovering of existing structure
Foundations (and any associated ground beams)
Oversite preparation and suspended floor
Damp-proof (or gas proof if required) membrane
Floor joists
Damp-proof course
Intermediate structure
Structural support
Roof structure
Drainage before covering
Insulation
Installation of new staircase
Drainage after covering
Fire spread prevention measures
Occupation
Certificate of completion
A certificate of completion will be issued when all work has been inspected, satisfactorily completed and we have received your completion notice.
This certificate is needed when selling the property or getting a mortgage. The certificate provides evidence to any prospective purchaser or mortgage company that building work has been carried out in accordance with building regulations.